Step-by-Step Guide

Installation Process

From first contact to flipping the switch, here's exactly what to expect when going solar with OnO Electric.

8-12 Weeks
Total Timeline
1-3 Days
Physical Install
0 Hassle
We Handle Everything

What Makes OnO Electric Different?

White-glove service from start to finish

We handle ALL permits and paperwork

Certified Master Electricians on every job

Clear communication every step of the way

Transparent pricing with no hidden fees

Comprehensive warranties on all work

Your Solar Journey Timeline

📞

Phase 1: Initial Consultation

1-2 Days
Step 1 of 8
  • Free phone or video consultation to discuss your energy goals
  • Review your recent utility bills and energy usage patterns
  • Preliminary roof assessment using satellite imagery
  • Provide ballpark cost estimate and financing options overview
🏠

Phase 2: Site Assessment

3-5 Days
Step 2 of 8
  • In-person site visit by certified solar consultant
  • Detailed roof inspection and structural evaluation
  • Shading analysis and sun exposure measurements
  • Electrical panel assessment for system compatibility
  • Take measurements and photos for system design
📐

Phase 3: Custom System Design

5-7 Days
Step 3 of 8
  • Create optimized solar array layout for your roof
  • Calculate precise energy production estimates
  • Select appropriate panels, inverters, and equipment
  • Design electrical wiring and connection schematics
  • Generate 3D renderings and production simulations
  • Provide detailed proposal with ROI analysis
✍️

Phase 4: Contract & Financing

1-3 Days
Step 4 of 8
  • Review and sign installation agreement
  • Finalize financing or payment arrangements
  • Complete rebate and incentive pre-applications
  • Schedule tentative installation date
  • Answer any remaining questions
📋

Phase 5: Permits & Approvals

3-6 Weeks
Step 5 of 8
  • Submit permit applications to City of Calgary
  • Coordinate with utility company for interconnection approval
  • Complete net metering application
  • Handle all building department requirements
  • Secure all necessary approvals before installation
  • Order equipment and schedule delivery
🔧

Phase 6: Installation

1-3 Days
Step 6 of 8
  • Delivery of solar panels and equipment to your property
  • Install mounting hardware and racking system
  • Mount solar panels and secure all connections
  • Install inverter(s) and electrical components
  • Run conduit and complete all wiring
  • Connect system to your electrical panel
  • Install monitoring equipment

Phase 7: Inspection & Activation

1-2 Weeks
Step 7 of 8
  • Schedule and pass city electrical inspection
  • Coordinate utility company final inspection
  • Receive Permission to Operate (PTO) from utility
  • Activate your solar system
  • Set up monitoring app on your devices
  • Provide system operation training
  • Hand over all warranties and documentation
🎉

Phase 8: Ongoing Support

25+ Years
Step 8 of 8
  • 24/7 system monitoring and performance tracking
  • Annual system health check-ups available
  • Warranty service and support
  • Production reports and energy savings updates
  • Answer questions anytime via phone or email
  • Coordinate any maintenance or repairs if needed

What Our Customers Say

"OnO Electric made the entire process seamless. They handled all the permits, rebate applications, and coordinated with the city. Installation was completed in 2 days and the system has been producing exactly as promised!"

— Michael T., Calgary SW

"From consultation to activation, the OnO team was professional, communicative, and incredibly knowledgeable. They answered every question and made sure we understood each phase. Couldn't be happier with our solar system!"

— Sarah & James K., Airdrie

Ready to Start Your Solar Journey?

Let's begin with a free consultation. We'll walk you through every step and answer all your questions.